2011.9监理质量检测月报(更改)

来源:华佗小知识


云南省 澜沧江

苗 尾 水 电 工 程

监理工程质量检测月报

(2011年8月份)

中国水利水电建设工程咨询昆明公司

苗尾水电站工程监理部

2011年8月28日

审 批:

校 核:编 写:

1

目 录

目 录 ·······························································································································································2 一、各标段工程形象进度 ··································································································································3 二、月度检测工作主要内容 ······························································································································4 三、8月份进场材料入库验收统计 ····················································································································4 四、原材料质量审批及抽检情况 ·······················································································································5 五、混凝土、喷混凝土、砂浆、净浆强度检测成果 ························································································6 六、锚杆、喷混凝土、混凝土工程实物质量检测 ····························································································7 七、8月份开挖质量检测情况 ························································································································· 10 八、混凝土拌和系统(站)生产质量控制情况 ······························································································ 10 九、其它检测事项 ············································································································································ 10 十、单元工程施工质量评定 ···························································································································· 11 十一、各标段违规、处罚跟踪统计表 ·············································································· 错误!未定义书签。 十三、结束语 ··················································································································································· 17

2

一、各标段工程形象进度

8月份各标段工程形象进度见表1:

表1 各标段工程形象进度表

施工单位 施工部位 工程主要形象进度 EL.1515~1525m高程完成喷混凝土185m3。 EL.1515~1505m高程完成坡面验收及喷混凝土70m3。 EL.1510m高程完成探洞回填混凝土600m3。 EL.1535m高程完成马道混凝土84m3;完成贴坡混凝土43m3。 EL.1515~1495m高程完成土石方开挖34000m3。 EL.1505m高程完成土石方开挖190000m3。 完成进水渠段回槽子侧锚杆(锚筋桩)施工300根。 EL.1353.4m高程完成马道及贴坡混凝土340m3。 EL.1338.4m高程完成马道及贴坡混凝土400m3。 EL.1474.8m以上完成锚索联系梁混凝土150m3。 EL.1474.8~1454.8m高程完成锚索联系梁混凝土130m3。 EL.1454.8~1434.8m高程完成喷混凝土204m3。 EL.1454.8~1434.8m高程完成土石方开挖13000m3;完成固结灌浆930m;完成锚筋桩132根:完成排水孔420m;完成锚索施工74根。 完成EL.1434.8~1474.8m高程侧坡面脚手架搭设。 完成EL.1360高程以上--厂左0+15~厂左0+85边坡锚筋桩施工50根;锚索施工40束;排水孔1285 m. 完成 EL.1400~1366m高程土石方开挖53000m3。 完成厂左15~厂右35上游侧坡面锚索施工56根;锚筋桩68根。 完成主动防护网5800m2; 完成EL.1414.8~1404.8m高程土石方开挖56000m3。 完成土石方开挖15000m3。 完成 EL.1470~1455m高程土石方开挖23000m3。 完成大块石备料11160m3;石渣料10068m3;中石15500m3;钢筋石笼120个。 完成左坝基供水、供电系统修建。 筛分车间完成土石方开挖50m3;冲洗车间完成土石方开挖74 m3;系3统胶带机完成土石方开挖399.18 m。 细碎车间完成混凝土196.72m3;超细碎车间及料仓完成混凝土342.77m3。 筛分车间完成混凝土16.8m3;三筛车间完成混凝土2.7m3。 冲洗脱水车间完成混凝土17.1m3;系统胶带机完成混凝土354.2m3。 浆砌石完成1130m3。 系统边坡支护完成360.96m3。 金结制作完成184.73t。 3

溢洪道 发电厂房厂前区 江南水利水电工程苗尾水电站大坝工程 大坝、溢洪道土建工程 右坝头工程 发电厂房后边坡开挖支护工程 左坝基工程 施工导流和水控制工程 引水进水口和冲砂兼防空洞进口开挖及支护工程 主要临建项目 水电 八局丹坞堑砂石项目部 系统土建 系统钢结构制安工程

二、月度检测工作主要内容

1.验收施工单位进场原材料;按照合同文件及有关规范要求,督促施工单位对进场原材料进行检验;审查批复施工单位报送的《原材料质量检验审批表》。

2.对施工单位使用的原材料和中间产品开展的监督性和复核性试验检测工作。 3.按照合同文件要求及规范、标准,督促施工单位开展全面试验检测工作,并严格要求施工单位按照经审批的质量检测计划、检测内容和检测频率进行试验检测,同时对施工单位试验室进行不定期检查。

4. 监理采取抽检和试验见证的方式,对各施工单位所进场原材料、中间产品、完工实物检测等重要关键环节按规定进行了试验检测控制。根据“三大中心”和监理检测数据,每月编制《实物质量检查报告》和《监理工程质量检测月报》。

5.8月份对各现有的零星拌和站(点)进行检查,并督促施工单位拌和站(点)必须采用重量法配料,每个拌和站必须配备经计量检定合格的电子秤或台秤等称量设备,确保拌和配料误差符合规范要求。

6.根据建管局工程质量管理相关规定,每月末由分管质量的副总监组织各方对各标段施工质量进行检查,检查内容主要涉及工程实物质量、外观质量、工艺控制、内业资料四个方面,对检查过程中发现的问题实事求是地提出整改要求,督促各施工单位限期整改,实现质量工作的闭环管理。

三、8月份进场材料入库验收统计

8月份各施工单位进场材料入库验收情况见表2: 表2 8月份进场材料入库验收情况表 材料名称 施工单位 入库验收情况 规格 石林三江P.C32.5 水 泥 江南水电 石林三江P.O42.5 大理红山岩P.O42.5 水电八局 石林三江P.O42.5 批次(批) 6 15 / 5 数量(t) 399 1499 / 300 4

材料名称 施工单位 入库验收情况 规格 大理红山岩P.O42.5 批次(批) / / / 12 39 / / 数量(t) / / / 58.454 265.436 / / 粉煤灰 江南水电 水电八局 江南水电 曲靖I级 曲靖I级 HPB235(昆钢) HRB335E(昆钢) 钢 筋 HRB335(昆钢) 水电八局 HRB335E(昆钢) 江南水电 其它材料 水电八局 江苏博特新材料有限公司JM-PCA(Ⅰ)型1批次12.1t;引气剂 GYQ(1) 1批次0.2t。 无粘结钢绞线1860Mpa(江西新华金属制品公司) 5批次91.752t。 / 四、原材料质量审批及抽检情况

8月份,监理部按相关规定对各施工单位进场原材料(水泥、钢筋、粗细骨料、外加剂)进行了抽检、审批。抽检和审批情况见表3:

表3 原材料质量检测审批情况表 2011年8月份 审批材料 施工单位 江南水电 水电八局 江南水电 水电八局 江南水电 水电八局 江南水电 水电八局 江南水电 水电八局 江南水电 审批批次 (批) 15 5 14 / 3 3 1 1 / / 审批量 (T) 1733 1138 231 / 1579 913.81 2325 1424.55 / / 监理抽检 (批) 3 1 4 3 3 3 1 2 / / 抽检率 (%) 20 20 28.6 100 100 100 100 200 / 水泥 钢筋 粗骨料 细骨料 粉煤灰 其它材料 江苏博特新材料有限公司JM-PCA减水剂1批次12.1t;引气剂 GYQ 1批次0.2t。 江西新华无粘结钢绞线2批次82 t。 8月份监理审批原材料46批次,抽检原材料20次,监理抽检率为43.5%;施工单位检测

5

钢筋接头3批次,监理抽检钢筋接头1次,抽检率为33.3%。抽样检测结果表明,各单位进场原材料符合有关标准,且自检频率和检测项目符合要求,检测资料齐全,进场原材料全部合格。

从检测结果看,监理部送检的窝嘠沟砂石加工系统9组样品中:人工砂3组,除细度模数超标外,其它检测指标满足规范要求;小石、中石、瓜米石检测6组,除1组小石、1组中石中径筛余、1组中石超径含量不满足规范要求外,其余超、逊径指标均满足规范要求。

五、混凝土、喷混凝土、砂浆、净浆强度检测成果

8月份各工程项目混凝土、喷混凝土、砂浆、净浆质量检测成果详见表4-1、表4-2、表4-3、表4-4。根据各单位试验检测月报及监理抽检的检测成果分析,8月份我部所监理的施工项目中,施工单位共有混凝土(喷混凝土、砂浆、净浆)强度检测成果68组(其中:江南水电大坝工程36组,中水八局砂石加工系统32组),监理部委托长科委中心实验室进行检测,共有检测成果17组(其中:江南水电大坝工程12组,中水八局砂石加工系统5组),总检测比例为25%。检测结果均满足设计及相关规范要求

表4-1 MIW/C2标段8月份江南水电混凝土(喷混凝土、砂浆、净浆)试验检测结果统计表 项目 设计标号 拌和系统 厂前边坡施工现场 C25 F100W8 回槽子沟施工现场 溢洪道施工现场 砼 C30 F100W8 右坝头施工现场 回槽子沟施工现场 C20 溢洪道施工现场 厂前边坡施工现场 喷砼 C25 厂后边坡施工现场 溢洪道施工现场 净浆 M40 厂后边坡施工现场 28 1 44.7 44.7 44.7 100 / / / 28 28 1 1 30.2 43.2 30.2 43.2 30.2 43.2 100 100 / / / / / / 28 28 3 2 26.7 31.2 25.0 28.7 26.0 30.0 100 100 / / / / / / 28 28 2 1 35.6 32.4 34.7 32.4 35.2 32.4 100 100 / / / / / / 28 28 1 9 30.8 37.1 30.8 33.0 30.8 35.0 100 100 / / / / / / 龄期(d) 组数 28 12 最大值最小值平均值保证率标准差PS(%) C(%) (Mpa) (Mpa) (Mpa) (%) (Mpa) V35.7 29.5 31.4 100 / / / 6

项目 砂浆 设计标号 M25 拌和系统 厂前边坡施工现场 龄期(d) 组数 28 3 最大值最小值平均值保证率标准差PS(%) C(%) (Mpa) (Mpa) (Mpa) (%) (Mpa) V46.8 37.4 40.9 100 / / /

表4-2 MIW/C2标段8月份监理单位混凝土(喷混凝土、砂浆、净浆)试验抽测结果统计表

项目 设计标号 拌和系统 进水渠施工现场 C25 F100W8 砼 厂前区施工现场 右坝头施工现场 进水渠施工现场 C30 F100W8 右坝头施工现场 喷砼 砂浆 净浆 C25 M25 M40 厂前区施工现场 厂后施工现场 厂后施工现场 28 28 28 28 1 1 1 1 44.1 28.8 28.7 44.0 44.1 28.8 28.7 44.0 44.1 28.8 28.7 44.0 100 100 100 100 / / / / / / / / / / / / 龄期(d) 组数 28 28 28 28 1 2 1 4 最大值最小值平均值保证率标准差PS(%) C(%) (Mpa) (Mpa) (Mpa) (%) (Mpa) V29.0 38.6 34.9 42.1 29.0 28.8 34.9 34.6 29.0 33.7 34.9 37.2 100 100 100 100 / / / / / / / / / / / / 表4-3 MIW2010/T16标段8月份水电八局混凝土试验检测结果统计表

项目 砼 设计标号 C25 拌和系统 1#、2#成品料仓施工现场 龄期(d) 组数 28 32 最大值最小值平均值保证率标准差PS(%) CV(%) (Mpa) (Mpa) (Mpa) (%) (Mpa) 30.9 26.2 27.9 100 98.9 1.141 0.041 表4-4 MIW2010/T16标段8月份监理单位混凝土试验抽测结果统计表

项目 砼 喷砼 砂浆 设计标号 C25 C20 M7.5 拌和系统 1#、3#成品料仓施工现场 R1公路、2#成品料仓施工现场 第二筛分车间施工现场 龄期(d) 组数 28 28 28 2 2 1 最大值最小值平均值保证率标准差PS(%) CV(%) (Mpa) (Mpa) (Mpa) (%) (Mpa) 32.5 37.9 28.0 29.5 26.2 28.0 31.0 32.0 28.0 100 100 100 / / / / / / / / / 六、锚杆、喷混凝土、混凝土工程实物质量检测

2011年8月份,江南水电进行了锚杆物探检测;监理工程师对各部位锚杆施工均按程序验收,抽查检测了锚杆造孔、锚杆长度,并委托长科委物探中心对溢洪道进水渠段的锚杆长

7

度和锚杆注浆密实度进行了抽检,检测结果表明各项指标均能满足要求。具体检测统计结果见表5、表6、表7。

表5 8月份施工单位锚杆自检成果表

施工 单位 检查部位 桩号及高程 设计 长度(m) 3.0 3 12.0 15.0 锚杆长度 注浆密实度 检测 单元评数量合格率定结果 最大值 最小值 平均值 最大值 最小值 平均值 (根) (%) 6 6 6 6 3.18 3.21 2. 2.94 3.03 3.02 100 87 91 93 78 73 71 70 87.2 80.2 82.5 83.3 100 83.3 83.3 83.3 合格 合格 合格 合格 中线公路边坡,K0+0.00~K0+090.00,EL.1351.8~EL.1368.4 中线公路边坡,K0+90~K0+129.5,EL.1352.65~江南公司 EL.1370.51 进水渠段K0-90.00~K0+15.35 EL.1515~EL.1525 12.07 11.87 11.96 15.18 14.88 15.01 表6 8月份监理抽检锚杆成果统计表

施工 单位 检查部位 锚杆类型 抽测 设计值根数 (m) 15 10 16 20 12 3.90 12 15 孔深 实测范围/实测深度 (m) 11.96~11.98 3.90~3.95 11.95~11.98 14.95~14.98 外露长度 实测平总体 总体 设计值总体 均值评价 评价 (m) 评价 (m) 满足满足满足设设计设计0.10 0.10 计要求 要求 要求 满足满足满足设计设计0.10 0.10 设计要求 要求 要求 满足满足满足设计设计0.10 0.09 设计要求 要求 要求 优良 优良 0.10 0.10 优良 孔向 发电厂房厂后区 3根Φ28 L=12m Φ25 L=4.5m 江南公司 进水渠 3根Φ25 L=12m 3根Φ25 L=15m 表7 监理委托锚杆检测成果表

施工 单位 检查部位 桩号及高程 溢洪道进水渠段K0+90.0~K0+153.4 EL.1515~EL.1525 设计 长度(m) 12.0 15.0 锚杆长度 注浆密实度 检测 单元评数量合格率定结果 (根) 最大值 最小值 平均值 最大值 最小值 平均值 (%) 6 6 11.96 11.43 11.67 15.09 14.56 14.88 95.3 94.1 78.8 87.3 86.0 90.8 83.3 100 合格 合格 江南公司 2011年8月份监理对江南水电的右坝头边坡、溢洪道进水渠边坡;中水八局的棒磨机制砂原来仓边坡支护、R1公路边坡喷混(二筛车间段)、三筛边坡支护均进行了喷混凝土厚度检测;并委托长科委物探中心对厂前边坡、溢洪道进水渠、1#成品料仓边坡支护、1#路(二筛段开挖边坡支护)、1#路(超细碎平台支护)、3#半成品及C2胶带机边坡开挖支护、值班

8

室支护部位的喷混凝土厚度进行了抽检,检测结果表明除右坝头边坡喷混凝土厚度不满足设计要求外,其他部位喷混凝土厚度均满足设计要求。具体检测统计结果见表8、表9。 表8 8月份监理喷混凝土厚度抽检成果表

检测部位 检测单元 EL.1473.8 坝下0+10 EL.1476.4 坝下0+7~0+8 EL.1526 K0~44.0 EL.1675~EL.1686.5 K0+0~K0+22 EL.1670~EL.1684 K0+179.5~K0+251.7 EL.1667~EL.1670 K0+00~K0+20 设计厚度(cm) 15 15 15 10 测点数平均厚度(点) (cm) 9 9 12 8 10.8 17.8 18.7 17.2 最小厚测点合格度(cm) 率(%) 7 17 8 13.0 0 100 83.3 100 评定 结果 不合格 合格 合格 合格 C2标 右坝头边坡 溢洪道进水渠段 棒磨机制砂原来仓边坡支护 R1公路边坡T16标 喷混(二筛车间段) 三筛边坡支护 10 26 14.1 10.2 100 合格 10 6 12.8 10.5 100 合格 表9 监理委托喷混凝土厚度检测成果表

检测部位 检测单元 EL.1326 K0-15~K0+5 EL.1326 K0+120~K0+140 EL.1518 B0+31~B0+51 EL.1652~EL.1667 K0+0~K0+124.8 EL.1670~EL.1684 K0+179.5~K0+251.7 EL.1675~EL.1691 K0+34~K0+468 设计厚度(cm) 18 18 15 10 测点数平均厚度(点) (cm) 200 200 200 250 24.0 24.0 16.6 12.3 最小厚测点合格度(cm) 率(%) 13.5 11.8 11.8 7.3 87.0 86.5 85.0 88.8 评定 结果 合格 合格 合格 合格 C2标 厂前边坡 溢洪道进水渠 1#成品料仓边坡支护 1#路(二筛段开挖边坡支护) 10 250 12.9 7.3 88.4 合格 T16标 1#路(超细碎平台支护) 10 250 12.4 7.1 86.0 合格 3#半成品及C2EL.1684~EL.1697 胶带机边坡开K0+0~K0+124.8 挖支护 值班室支护 EL.1652~EL.1667 K0+0~K0+30.9 10 200 13.3 7.3 86.5 合格 10 200 13.9 7.6 94.5 合格 9

七、9月份开挖质量检测情况

监理部针对现阶段监理工程的特点,对开挖成型断面的平整度以及超欠挖情况进行检测,检查、检测数据记录在案,作为开挖质量评定的直接依据,以及时指导处理开挖中碰到的有关问题。检测统计数据如表10、表11所示。

表10 9月份开挖验收单元平整度统计表

施工单位 检查部位 上游围堰左防渗体 EL.1341.6m~1321.5m 江南公司 右岸坝头 EL.1414m~EL.1434m 左坝肩 EL.1406.6m~1414.8m 检测点数 最大值(cm) 30 24 30 21 28 22 最小值(cm) 4 8 3 平均值(cm) 12 18 12 表11 9月份开挖验收单元超、欠挖检测成果表

施工 单位 检测部位 上游围堰左防渗体 EL.1341.6m~1321.5m 江南 公司 右岸坝头 EL.1414m~EL.1434m 左坝肩 EL.1406.6m~1414.8m 平均超挖检测 平均超挖 最大平均超最小平均最大超挖≤20cm的断面断面 (cm) 挖(cm) 超挖(cm) 点(cm) 比例(%) 15 13 24 7 80 12 21 27 12 75 15 14 24 8 52 80 注:上表中超挖数据包含地质原因引起的超挖。 八、混凝土拌和系统(站)生产质量控制情况

拌合系统正在筹备中。

九、其它检测事项

1、审查、批复各施工单位报送的砼配合比,并用于各标段施工中。 2、旁站各施工单位室内部分重点试验的过程。

3、严格按照测量监理细则及相关规范,对施工放样、控制测量和开挖验收断面测量等项目进行旁站和一定比例的抽测;对各施工单位配备的测量人员数量及资质、仪器设备的依法检定情况进行实时监督检查。对我部监理的部分进水渠项目、左岸、右岸边坡的变形观测进行旁站,并审核上报成果;及时对边坡开挖原始地形、收方地形、开挖断面进行测量检测;

10

审查测量内业资料,批复测量文件;

4、按照相关规范及技术要求,对进水渠、右坝头工程的原型观测的仪器的进场进行了验收、对仪器的安装埋设过程进行了旁站、对现场数据采集进行了抽样检查、对报送的监测成果进行了内业审核。

5、按照业主相关规定,及时组织对施工单位的施工质量考核,并对考核中的实物工程质量进行抽样检测,并形成《实物检测报告》。

6、检查施工单位质量保证体系和“三检制”运行情况,督促施工单位在施工中进一步落实质量管理有关制度,不断完善质量保证体系。

十、单元工程施工质量评定

按照《监理实施细则》和单元工程质量验收评定标准,在进行工序和单元工程验收时,现场监理工程师对其中的检查检测项目,如钢筋间距、模板平整度、钻孔深度、方向、排水孔长度等进行抽检,复核施工单位提交的自检资料,并对工序和单元工程施工质量进行评定。2011年8月份验收单元工程60个,其中优良52个,验收评定合格率100%,验收评定优良率86.7%。评定情况详见表12、表13。

表12 8月份单元工程质量验收、评定统计表

施工 工程项目 单位 名称 江南公司 溢洪道工程 分部工程 分项工 名称 程名称 进水渠边坡开挖工程 截水沟浆砌石 溢洪道工程 江南公司 进水渠锚喷支护工程 进水渠混凝土工程 右岸坝肩边坡开挖与支护 截水沟浆砌石 右岸坝头边坡开挖工程 验收评定合计 八局项丹坞堑砂石加目部 工系统 土建工程 混凝土 开挖 浆砌石 支护 混凝土 浆砌石 开挖 本月验收单元情况 验收单优良单合格率元工程元工程(%) (个) (个) 1 1 3 22 1 1 29 31 100 100 100 100 100 100 100 100 1 1 2 18 1 1 24 28 优良率 (%) 100.0 100.0 66.7 81.8 100.0 100.0 82.8 90.3 自开工以来该分部工程中单元工程优良率(%) 100.0 80.0 80.0 82.8 100.0 100.0 88.7 92.6 11

施工 工程项目 单位 名称 分部工程 分项工 名称 程名称 验收评定合计 本月验收单元情况 验收单优良单合格率元工程元工程(%) (个) (个) 31 100 28 优良率 (%) 90.3 自开工以来该分部工程中单元工程优良率(%) 92.6 十一、各标段违规、处罚跟踪统计表

8月份各标段违规、处罚跟踪统计见表14。

12

13

表14 8月份质量违规整改、处罚跟踪统计表

序号分类 罚整改款 结果/金跟踪额 检查(元) 情况 发文时间 文 号 问题来源 工程部位 存在问题及整改要求

1 2 监理2011.08.02 通知单 昆咨苗监通知[2011]051号(通知C2总第052号) 质检人员工作不认真,不仔细,未严格按照施工技术要求施工。 右坝头EL.1454.8~EL.1434.8 右坝头EL.1454.8~EL.1434.8固结灌浆施工前未向监理报检就自行灌浆,并且现场质检人员不提供灌浆自动记录资料。 要求江南公司领导和质量部门负责人对右坝头固结灌浆施工质量引起高度重视,严格按照上一道工序验收合格后才能进入下一道工序的施工。为使今后的质量管理工作不出现类似事件,确保工程质量,要求加大质量管理人员加强切实质量管理力度并严格把关,所有工序经监理工程师验收合格后现场进行验收资料签证。 进水渠爆破器材仓库未装报警系统、未设消除静电装置、消防砂池存储量小、库房台账不完善、涉爆人员必须持证上岗。 要求建立报警系统和设置除静电装置;对不能满足安全要求的消防砂存量不足应在炸药库附近再修建一个消防池,池中应储满消防砂并配备相应工具;加强爆破器材领用人员管理制度,建立领用人员档案,并将涉爆人员的有效资质证书报监理部备案。 / 已进行整改 监理2011.08.02 通知单 昆咨苗监通知[2011]052号(通知C2总第053号) 安全管理不足、安全意进水渠炸药仓库 识薄弱。 / 正在整改中 14

序号发文时间 分类 文 号 问题来源 工程部位 存在问题及整改要求 罚整改款 结果/金跟踪额 检查(元) 情况

3 4 5 监理2011.08.17 通知单 昆咨苗监通知[2011]054号(通知C2总第055号)、昆咨苗监通知[2011]056号(通知C2总第057号) 对统供物资的申领、现场保管不规范。 监理2011.08.22 通知单 昆咨苗监通知[2011]052号(通知C2总第053号) 质量管理不到位,施工组织不力。 监理2011.08.22 通知单 昆咨苗监通知[2011]006号(通知T16总第006号)、昆咨苗监批复[2011]040号(批复T16总第040号)、 对统供物资的现场保管不规范及拌和称量不准确、加水随意性较大。 在无统供物资仓库的情况下,对统供物资的申领、现场保管的管理制度不完善;厂后区、右坝头混凝土浇筑时,不重视对统供材料的保护。特别是在右坝头随意踩踏钢筋,厂后区砂石骨料经装载机运后混有泥土。以C2标各施工物资堆放点 上行为均对统供物资的浪费,同时也对施工质量留有一1000 定的隐患。 要求项目部对现场统供物资堆放必须做到能够防汛、防潮、防盗的要求;切实做好统供油料、统供物资的规范化、制度化管理。 进水渠在进行回填灌浆施工时,施工人员不能提供真实有效的灌浆过程记录,灌浆过程中灌浆压力及参数未打单设计要求。出现以上问题质检人员不闻不问,形进水渠EL.1515~ 同虚设。 EL.1505(PD探洞)灌/ 要求项目部工程科、质量科联合对施工班组进行技浆现场 术交底,质量管理人员加强现场质量管控力度。现场应及时、真实、准确地进行制浆记录并严格按照配合比制浆。 丹坞堑加工系统2#成品料仓地弄边墙顶板EL: 19.75~EL: 1653.25在混凝土拌和过程中未严格按照配合比施工,拌和称量不准确、拌和加水随意性较大;现场钢筋母材堆放点未设置任何防雨设施,导致部分钢丹坞堑砂石加工系统 筋生锈;水泥堆放点未做到上铺下垫,部分水泥结块变2000 硬造成统供物资的浪费。 要求项目部对现场统供物资堆放必须做到上铺下垫,对钢筋进行除锈后才能用到工程中,现场严格按照配合比施工,加强混凝土生产全过程质控制,树立严谨15

已进行整改 已进行整改 已进行整改 序号发文时间 分类 文 号 问题来源 工程部位 存在问题及整改要求 罚整改款 结果/金跟踪额 检查(元) 情况

的工作作风。 16

十三、结束语

综合8月份检测情况及试验结果分析,由我监理部所监理的江南水电苗尾大坝工程、水电八局苗尾砂石工程的施工过程总体处于受控状态,施工质量控制较好,施工资料基本齐全,工程施工质量符合合同文件要求。

中国水利水电建设工程咨询昆明公司苗尾水电站工程监理部

2011年8月28日

17